Project Information
Version 17.1 by Mohamed Elsayed on 2023/04/09 17:37
Group Members
| Name | Role |
| Mohamed Elsayed | Note Taking/ Deadline Manager / Arrange Evaluation |
| Mees van der Lecq | Graphic Designer/ Developer |
| Rick Dekker | ROS/ MiroCode Developer / Statistical Analyst |
| Clemente van der Aa | Team Leader/ XWiki Expert |
Work Progress
| Task | Member | Date |
| Effect | Clemente | Week 1 |
| Storyboard | Mees | Week 1 |
| Claims | Mohamed | Week 1 |
| Specify Functions | Rick | Week 1 |
| Week 2 | - | - |
| Write Use Case | Clemente | Week 2 |
| Environment /Personas | Mees | Week 2 |
| Operational demands/ Environment / Problem Scenario | Mohamed | Week 2 |
Research about Miro-e functionalities/ Functions, Specify Use Case: interact with patient | Rick | Week 2 |
| Week 3 | - | - |
| Prototypes | Clemente | Week 3 |
| Design Scenario/Presentation | Mees | Week 3 |
| Human Factors/ Improving XWiki / Presentation | Mohamed | Week 3 |
| Work on Presentation/Technology analysis | Rick | Week 3 |
| Week 4 | - | - |
| Clemente | Week 4 | |
| MiroCloud simulation programming start | Mees | Week 4 |
| Human Factors / Work on presentation / Specifications | Mohamed | Week 4 |
| Try programming Miro-e in ROS, switch to MiroCloud programming | Rick | Week 4 |
| Week 5 | - | - |
| Change of direction. rewrite corresponding chapters like use case and prototype | Clemente | Week 5 |
| Programming done/Real-world testing | Mees | Week 5 |
| HRI prototyping Software / Claims | Mohamed | Week 5 |
| Finish up programming, Start debugging and finetuning experiment. | Rick | Week 5 |
| Week 6 | - | - |
| Prepare final presentation | Clemente | Week 6 |
| Evaluation mood questions/final programming before evaluation | Mees | Week 6 |
| Final Presentation/ Set up experiment / conduct evaluation / Write Consent form | Mohamed | Week 6 |
| Research Trust score, do final bug fixes before evaluation/Conduct experiments | Rick | Week 6 |