1 **Planning Week 1**
2 * Researching on target audience (types and stages of dementia) = Ines DONE
3 * Researching on location & goal of interaction = Pierre DONE
4 * Researching on group vs. individual activities = Haoran DONE
5 * Researching on technologies for the elderly = Mathieu DONE
6 * Researching on robot agents (features available to us and previous use cases) = Sneha & Manolo DONE
7 * Meeting to put all the info together and decide on the specifics for the project = Everyone DONE
8
9 **Planning Week 2**
10 * Getting started with Choregraphe and trying to program the activity breakdown help = Manolo & Mathieu DONE
11 * Getting started with Choregraphe and trying to program the calendar/reminder feature = Pietro & Haoran DONE
12 * Updating the wiki regarding week 2 schedule (Specification tab + Operational demands + Music) = Sneha & Pierre DELAYED
13
14 **Planning Week 3**
15 * Implementing a first version of the activity help feature = Manolo & Mathieu DONE
16 * Implementing a first version of the reminder feature = (Pietro & Haoran) Mathieu DONE
17 * Updating the wiki (All Foundation tab (+Objectives, Claims, Planning as extras)) = Mathieu DONE
18 * Implementing music behaviour = Pietro DELAYED
19 * Doing the design pattern and ontology = Sneha & Pierre PARTIALLY DONE
20 * Finishing the Specification tab = Sneha & Pierre PARTIALLY DONE
21
22 **Planning Week 4**
23 * Doing the design pattern and ontology = Sneha & Pierre DONE
24 * Finishing the Specification tab = Sneha & Pierre DONE
25 * Implementing music behaviour = Pietro DONE
26 * Testing the behaviours with an actual Pepper robot = everyone DONE
27 * Making photos/videos of the testing = everyone DONE
28 * Preparing the presentation for week 5 = Mathieu, Manolo, Pierre DONE
29 * Making the evaluation plan = Haoran, Pietro, Manolo DONE
30
31 **Planning Week 5**
32 * Presenting = Mathieu, Manolo, Pierre DONE
33 * Updating wiki = Pierre & Sneha DONE
34
35 **Planning Week 6**
36 * updating wiki = everyone IN PROCESS
37 * making tablet visuals = Manolo DONE
38 * finding evaluation activities = Pietro & Sneha DONE
39 * planning and preparing the evaluation = Haoran & Mathieu DONE
40 * testing everything with Pepper to be ready for the evaluation = everyone DONE
41
42 **Planning Week 7**
43 * organizing evaluation sessions = Mathieu IN PROCESS
44 * conducting the evaluation = everyone TO DO
45 * analyzing results = TBD TO DO
46 * preparing presentation = TBD TO DO
47
48 **Planning Week 8**
49 * presenting = Pietro, Haoran, Sneha (+ TBD?) TO DO